News Update - Construction Projects and Works for 2025-2028

Update - Construction Projects and Works for 2025-2028

Bike Network Section

Most of the planned bike network improvements have been completed. Only two sections could not be completed, namely on Lucerne and in the Town centre; they will be finalized as soon as Hydro-Québec and the REM have completed their work.

Here is an update on the planned work:

  • Marlboro/Eden section – completed
  • Graham Blvd (between Glengarry and Lombard) section – completed
  • Rockland Road (corner Brookfield) crossing – completed
  • Devonshire/Côte-de-Liesse intersection – completed
  • Royalmount section – terminé
  • Cornwall bridge section – awaiting completion of REM construction
  • Laird bridge section – awaiting completion of REM construction
  • Lucerne section (between Côte-de-Liesse and Plymouth – awaiting completion of Hydro-Québec construction

Completed Construction and Works

Several maintenance and repair works were undertaken and completed throughout the city this summer. 

Below are a few examples:

  • Paving work on Canora and Graham in the Town centre – completed
  • Jacketing of the water main network in the Town centre – completed
  • Jacketing of the water main network on Plymouth – completed
  • Lighting for the tennis courts at Mohawk Park – completed
  • Library roof repair – completed
  • Installation of four charging stations in the underground and outdoor parking lots at City Hall – completed

For information on current and upcoming construction projects and works, please consult the Info Constructionsection for full details.

Mid- to Long-Term Works

Several projects are underway or planned for 2025 to 2028:

  • Reconstruction of the front steps of Town Hall – underway, completion scheduled for fall 2025
  • Renovation of tennis courts at Mohawk Park – underway, completion scheduled for spring 2026
  • Construction of the new S Community and Sports Centre (SCC) – underway, completion scheduled for spring 2028
  • Reconstruction of the street and Hydro-Québec work on Bates Road – underway and scheduled for completion in spring 2026
  • Redevelopment of the Norway/Kindersley intersection – underway and scheduled for completion by the end of October 2025
  • Construction of a new fire station and administrative offices on Roosevelt Avenue – work to begin in fall 2025 and scheduled for completion at the end of 2027 
  • Redevelopment of the Churchill/Montgomery/Glencoe intersection – underway, fall 2025
  • Noise barrier along the REM on Dunkirk and Canora, between Côte-de-Liesse and downtown – work scheduled for spring/summer 2026
  • Repair of architectural concrete at the library – work to begin in spring 2026 and scheduled for completion in fall 2026
  • Installation of two public electric vehicle charging stations in the Town centre – summer 2026
  • Energy-saving measures for buildings in Danyluk Park – work to begin in summer 2026 and scheduled for completion in fall 2026
  • Repair of the Cornwall Bridge – pending completion of REM work
  • Repair of the Laird Bridge – pending completion of REM work