Where would you like to
share this page?

News Construction Notice from Hydro Quebec - Installation of an Underground Power Transmission Line: Jean-Talon West Street and Lucerne Road

Construction Notice from Hydro Quebec - Installation of an Underground Power Transmission Line: Jean-Talon West Street and Lucerne Road

Jean-Talon West Street

Hydro-Québec will be conducting work on Jean-Talon West Street, between Lucerne Road and Saint-Clare Road, to install an underground electricity transmission line. This project is part of a larger effort to meet growing energy demand and ensure long-term service reliability on the Island of Montreal.

Work period: April 28 to May 16, 2025
Schedule: Monday to Friday, from 7:00 to19:00
Some weekend work may also take place.

Nature of the work:

  • Open trench excavation to install underground conduits.

Expected impacts:

  • Partial closure of Jean-Talon West Street

  • Temporary removal of parking spaces

  • Machinery noise during certain operations

  • Secured construction zone

Mitigation measures:

  • Clear signage in place

  • Access to homes and businesses maintained

  • Pedestrian access preserved

  • Traffic control personnel on site as needed

  • Fencing installed around the work zone

Lucerne Road

To meet the growing demand for electricity and ensure the long-term reliability of its infrastructure on the Island of Montreal, Hydro-Québec will be installing an underground power transmission line between the Mont-Royal and Saraguay substations.

Work period: from April 30 to September 5, 2025
Schedule: Monday to Friday, from 7:00 to19:00
Some weekend work may also take place.

Work zone and scope:

  • Construction of underground ducts and installation of junction boxes
  • Lucerne Road: between Jean-Talon West and Chemin de la Côte-de-Liesse

Impacts:

  • April 30 to May 9: two-way traffic maintained on Lucerne Road
  • May 12 to September 5: northbound Lucerne Road closed; southbound traffic toward Jean-Talon West maintained
  • Removal of parking spaces in the affected zone
  • Occasional noise from machinery operations
  • Safety measures in place including signage and maintained access to homes and businesses

Mitigation measures:

  • Provide appropriate signage 
  • Maintain access to homes and businesses at all times 
  • Pedestrian access maintained 
  • Flagmen and flagwomen present as needed to ensure safe traffic flow around the worksite 
  • Installation of site fencing to separate work area from pedestrian passageway 

Please note: No power outages are expected during this work.

Crossing Côte-de-Liesse Road under Highway 40

To ensure the long-term operability of its facilities on the island of Montreal, and to meet growing demand for electricity in the area, Hydro-Québec is building an underground transmission line between Mont-Royal substation (Côte-des-Neiges-Notre-Dame-de-Grâce borough) and Saraguay substation (Saint-Laurent borough).

The work involves laying open-trench underground conduits under Highway 40 to link Avenue Sainte-Croix and Chemin Lucerne. 

Work period: early June to late August

Schedule: weekends only

Work duration for each phase will be three weekends. Work phases and impacts:

  1. Phase 1:Côte-de-Liesse crossing westbound Complete closure of avenue Sainte-Croix between rue Dion and chemin de la Côte-de-Liesse 
  2. Phase 2: Crossing under the A40 viaduct Partial closure of northbound traffic to cross the A40 (one lane maintained) 
  3. Phase 3: Côte-de-Liesse crossing westbound Partial closure of chemin Lucerne, one contra-flow lane maintained

For information:
Project Info Line: 1 866 388-1978
affairesregionales@hydroquebec.com
To report an outage or emergency: 1 800 790-2424

Consult the Info-Travaux (french only): Jean-Talon West Street

Consult the Info-Travaux (french only): Lucerne Road

Consult the Info-Travaux (french only): Crossing Côte-de-Liesse Road under Highway 40

Next news
Miscellaneous
April 28, 2025
It's Time to Protect Your Home Before the Heavy Rainfall Season
Read more

Similar news