September 14, 2023
- Roads and maintenance
- REM

The Réseau express métropolitain (REM) issued a news release on September 13 to provide an update on the latest developments in the project.
It includes a review of the first few weeks of operation, the next stages of construction and a financial update on the project.
Highlights
- More than one million passengers served on the South Shore antenna, with a 99% service reliability rate in the first few weeks.
- 67 km of network, including 17 km already in service, 85% completed in an unprecedented context.
- Additional costs of $1.65 billion, representing a 26% increase over the cost presented when bidders were selected, for a total of $7.95 billion.
- Excluding the exceptional $800 million impact of the pandemic, the cost increase is limited to 13%.
Full details
If you have any questions, please consult the REM news release or contact the organization directly using the information provided below.