Revere Avenue

The Town of Mont-Royal will reconstruct the road and sidewalks on Revere Avenue, between Rockland Road and Selwood Road. We expect the work to be completed approximately four weeks following the starting date.

  • Start date: Monday, July 6
  • Duration of work: 4 weeks

Melbourne Avenue

The Town of Mont-Royal will reconstruct the road and sidewalks on St-Clare Road, between Graham Boulevard and Mitchell Avenue. We expect the work to be completed approximately two to three weeks following the starting date.

  • Start date: Wednesday, August 5
  • Duration of work: 2 to 3 weeks

Here and there

The Town of Mont-Royal will conduct crack sealing work at various locations across town. The work typically takes 2-3 days to complete.

  • Start date: Thursday, July 30