• Roads and maintenance
  • Info construction

Laird Boulevard

The Town of Mount Royal will resurface the road and reconstruct the sidewalks on Laird Boulevard, between St-Clare Road and Geneva Crescent. We expect the work to be completed approximately four weeks following the starting date.

  • Start date: Wednesday, June 9
  • Duration of work: 4 weeks

Trenton Avenue

The Town of Mount Royal will resurface the road and reconstruct the sidewalks on Trenton Avenue, between the western Town limit and Aberdare Road. We expect the work to be completed approximately three weeks following the starting date.

  • Start date: Wednesday, June 9
  • Duration of work: 3 weeks

Ellerton Avenue

The Town of Mount Royal will resurface the road and reconstruct the sidewalks on Ellerton Avenue, between Rockland Road and Selwood Road. We expect the work to be completed approximately four weeks following the starting date.

  • Start date: Thursday, June 10
  • Duration of work: 4 weeks

Rockland Road

Bell Canada will work on Rockland Road, at the corner of Dunbar. Southbound traffic on Rockland will be blocked completely between Dresden and Beaumont. We expect the work to be completed approximately two to three weeks following the starting date.

  • Start date: Wednesday, June 16
  • Duration of work: 2-3 weeks

Andréa Delisle

Project engineer

40 Roosevelt Avenue

Mont-Royal H3R 1Z4

Hala Gébrine

Project engineer

40 Roosevelt Avenue

H3R 1Z4