• Roads and maintenance
  • Info construction

Ellerton Avenue

The Town of Mount Royal will resurface the road and reconstruct the sidewalks on Ellerton Avenue, between Rockland Road and Selwood Road. We expect the work to be completed approximately four weeks following the starting date.

  • Start date: Thursday, June 10
  • Duration of work: 4 weeks

Rockland Road

Bell Canada will work on Rockland Road, at the corner of Dunbar. Southbound traffic on Rockland will be blocked completely between Dresden and Beaumont. We expect the work to be completed approximately two to three weeks following the starting date.

  • Start date: Wednesday, June 16
  • Duration of work: 2-3 weeks

Dawson Avenue

The Town of Mount Royal will resurface the road and reconstruct the sidewalks on Dawson Avenue, between St-Clare Road and Fulton Road. We expect the work to be completed approximately three weeks following the starting date.

  • Start date: Monday, June 21
  • Duration of work: 3 weeks

Cornwall Avenue

The Town of Mount Royal will resurface the road and reconstruct the sidewalks on Cornwall Avenue, between Dumfries Road and Dunraven Road. We expect the work to be completed approximately three weeks following the starting date.

  • Start date: Monday, June 28
  • Duration of work: 3 weeks

Sherwood Crescent

The Town of Mount Royal will resurface the road and reconstruct the sidewalks on Sherwood Crescent, between Laird Boulevard and Graham Boulevard. We expect the work to be completed approximately three weeks following the starting date.

  • Start date: Monday, July 5
  • Duration of work: approximately 3 weeks

Saint-Clare Road

The Town of Mount Royal will carry out the resurfacing of the street and the reconstruction of the sidewalks on Saint-Clare Road, between Mitchell and Lazard. We expect the work to be completed approximately three weeks following the starting date.

  • Start of sidewalk work: July 7
  • Duration of work: approximately 2 weeks
  • Start of pavement work: August
  • Duration of work: approximately 1 week

Morrison

The Town of Mount Royal will begin pavement resurfacing and sidewalk reconstruction on Morrison Avenue between Winton and Dunkirk. Work is expected to be completed approximately two weeks after the start date.

  • Sidewalk start date: July 12
  • Duration of work: approximately 2 weeks
  • Pavement start date: August
  • Duration of work: approximately 1 week

Paré Street

The Town of Mount Royal will carry out the resurfacing of the street and the reconstruction of sidewalks on Paré Street.

  • Start of pavement work: 21 July
  • Duration of work: approximately 2 weeks

Andréa Delisle

Project engineer

40 Roosevelt Avenue

Mont-Royal H3R 1Z4

Hala Gébrine

Project engineer

40 Roosevelt Avenue

H3R 1Z4